Charlotte Extends Data Center Freeze Through 2027

0

Charlotte city leaders have just frozen all approvals for new data centers until October 2027, giving city leaders nearly another year to confront the industry’s rapid expansion.

City Council voted unanimously Monday to extend its temporary moratorium through Oct. 18, 2027. The original 150-day pause was scheduled to expire Nov. 5.

The moratorium blocks Charlotte from accepting, processing or approving applications for new data centers. Existing facilities and projects approved before the June moratorium can continue.

That leaves a major amount of development untouched.

Charlotte already has about 5.5 million square feet of data centers approved or under development, according to city officials. Some projects are massive hyperscale campuses designed for cloud computing and artificial intelligence.

Why Charlotte Hit the Brakes

Data center construction has accelerated as artificial intelligence drives demand for enormous computing capacity.

The facilities can consume huge amounts of electricity and require extensive cooling systems. Residents have also raised concerns about water use, constant mechanical noise, pollution and impacts on nearby neighborhoods.

One proposed Charlotte development, PowerHouse Charlotte, could eventually span five buildings across 122 acres. Opponents have estimated its power demand at 300 to 400 megawatts — roughly comparable to the electricity used by hundreds of thousands of homes.

Charlotte created its first moratorium in June to study those impacts and develop new rules.

City Wants Stronger Rules Before More Projects Arrive

The extended pause gives planners time to examine setbacks, noise standards, infrastructure capacity and other zoning restrictions.

City leaders are also watching Raleigh.

Current North Carolina law limits how aggressively cities can make existing zoning more restrictive. Charlotte officials hope state lawmakers will give local governments additional authority to regulate data centers.

State lawmakers are also considering broader data center legislation, including a proposed statewide pause.

Charlotte could end its moratorium early if new regulations are completed before October 2027.